Project Name: Pavement Management 2018 Project

  Project No.: CIP 5560
 
  Date: May 8, 2018
 
  Project Manager: Daniel Chavarria, (925) 973-2681
  Total Contract Value:
$2.85M
 

No. CONTRACTORS TOTAL BID
1 O'Grady Paving
$2,995,872.75
2 DeSilva Gates
$3,594,835.00
3 Granite Construction
$3,652,926.45
4 Bay Cities
$4,126,544.00

 

Project Name: Dougherty Valley GHAD On-Call Weed Abatement Services

  Project No.:
 
  Date: April 6, 2018
 
  Project Manager: Shane Hsieh, (925) 973-2675
  Total Contract Value:
$350,000
 

No. CONTRACTORS TOTAL BID
1 H&N Enterprises
$72,271