End Date Maintenance and Closures Start Date
Sep 28, 2022 TRAFFIC ALERT: There will be night work on Dougherty Road and Bollinger Canyon Road as part of the Pavement Management 2022 Project. One lane will be open to traffic during construction; however, motorist will be subject to delays. The working hours are from 9:00 PM to 5:00 AM, weather permitting. Please use caution when driving in the area. The tentative schedule is as follows:

Thursday, September 22nd - grinding of the roadway surface beginning on Dougherty Road

Sunday, September 25th - continuation of the grinding of the roadway surface that was not completed on Thursday night

Monday, September 26th - paving work will begin on Dougherty Road

Tuesday, September 27th - completion of the paving on Bollinger Canyon Road

Location Map
 Sep 22, 2022
Oct 2022 PG&E Gas Line Replacement Project - Twin Creeks South Unit 3 Subdivision Area Jan 2021
Dec 2022 Notice of Construction - Camp Bow Wow Mar 2022
Dec 2022  Notice of Construction - Comcast XNET Project - Citywide  July 2020
Jun 2023  Notice of Construction - PG&E Underground Service Installation (San Ramon Valley Blvd and Westside Drive) Sep 2021
Dec 2023 Crow Canyon Road Widening Project (webpage link)

Construction Notice - June 13, 2022

Construction has started. Please use caution when driving in the area. 

Jun 13, 2022
Nov 2022

TRAFFIC ALERT:  Alameda County work on Crow Canyon Road, west of Bollinger Canyon Road for their Storm Damage Repair Project begins the week of August 21st.  Anticipated completion is by end of November 2022. The work requires control of vehicular traffic during work hours and will impact the area from 7:30 AM to 3:30 PM, Monday through Friday. Expected delays varying from 15-45 minutes, depending on the time of day during construction hours.

Contact Alameda County at: [email protected] or call (510) 670-5591

Aug 21, 2022

Dec 2022

Pavement Management 2022 Project and Citywide Bicycle Network Improvements and Enhancements 

Planned Dates: September 2022 through December 2022   

Hours: 8:00 AM to 4:30 PM (unless otherwise posted).

In order to extend the service life of your street and improve the appearance and skid resistance, the City of San Ramon has contracted with MCK Services, Inc. to resurface streets in your area. We appreciate your cooperation in this matter and will do our best to minimize the inconvenience to your homes and businesses. 

Lane closures and detours will be set-up that may affect your normal parking, driving routes, and travel times. It is advised to allow additional time for travel during the duration of the construction. 

If you need assistance, or have conflicts/questions with the work, please call City of San Ramon, Public Works Department, Engineering Services Division main line, (925) 973-2670, or Suzy Edwards, Project Manager, at (925) 973-2667. Contractor: MCK Services, Inc. 865 Howe Road, Martinez, CA 94553 (925) 957-9200.

Sept 6, 2022